North Mare Island Levee Repair

Heavy equipment North Mare Island levee repair

Mobilization; setup and maintenance of wildlife exclusion fencing; developing and implementing a water pollution control program; excavating a starter trench and removing oversize material or debris which could impede the installation of sheet piles; installing sheet piling through the existing levee; backfilling the starter trench and excavated areas with controlled low strength material; placing and compacting fill to bury the top of the sheet piles; and installing erosion and sediment control measures.

CLIENT: Hanford ARC (sub) for North Wind Construction Services

DATE OF START: 3/08/2021

DATE OF COMPLETION: In Progress